Feature 1 of 8 · Portfolio

Portfolio & Health

One view of every project you answer for, grouped by client and programme, and each project judged on what its contract actually pays for. Leaders see where to look first and why, without asking for a status update.

3Health dimensions
4Delivery models
6Early warnings
DailyRating history

The idea in one minute

Most portfolio views judge every project against the same yardstick. PMO Assist doesn't. A fixed-price project lives or dies on schedule; a dedicated-capacity team on whether the seats are filled; time and materials and managed service on whether work is flowing. Each project's overall health is the dimension its delivery model is paid on, and a red anywhere else still pulls a green project down to amber, so nothing serious hides behind a good headline.

How the portfolio is organised

LevelWhat it is
AccountThe client. People hold a role on it: Viewer, Manager, Admin or Owner.
ProgrammeA body of work under one account. Optional.
ProjectWhere delivery happens: work, sprints, releases, milestones, team.
WorkstreamThe whole project, or each epic, chosen when the project is created. Releases, milestones and the weekly status follow it.
Delivery modelHow it is contractedJudged on
Fixed priceAgreed scope for an agreed fee. Overruns cost margin.Schedule
Dedicated capacityThe client buys allocated capacity.Staffing
Time & materialsThe client pays for hours actually logged.Flow
Managed serviceA recurring fee for run and support, against service levels.Flow
Honest by design

A project with no delivery model is left out of portfolio figures rather than guessed at. A dimension with nothing to judge reads Not enough data, never green.

The three health dimensions

Each is rated On track, At risk, Off track or Not enough data, with the reason beside it.

DimensionMeasuresOff trackAt risk
ScheduleMilestones against their committed baselinesAny milestone overdueAny at risk
StaffingHours reserved against hours the work needs, next four weeksShort by a quarter or more, or nobody allocatedShort by less, or people reserved with no planned work
FlowOpen work past its due date30% or more overdue10% or more

The rating is kept once a day. Each one says how long it has stood and what it was before (At risk for 9 days, was on track), and when a project gets worse, its lead and its account's managers are told once, with the reason.

Warnings before the rating turns

WarningWhen
Due soonAn open milestone's baseline is within 7 days.
Still movingA milestone's expected date slipped at each of the last three weekly readings, or it was re-baselined twice or more.
Release at riskThe next release is due within 14 days and too little of it is done.
Stale blockerThe same item is a blocker in the two latest published weekly reports.
Gone quietNo weekly status published in 14 days, or no time logged in 7 working days.
Report out of dateThe last delivery report called a better status than health reads now.

Where leaders work

The Portfolio has its own sidebar. Pick the accounts, programmes or projects at the top, and every page follows.

PageThe question it answers
OverviewThe whole picture, in the order it is read: key figures, needs attention, health, milestones and releases, staffing and budget, blockers and sprints, reports.
Needs attentionEverything that is wrong, act-now before watch, with one link each.
HealthHow each project is rated, why, for how long, and the next step.
Milestones · Releases · SprintsWhat is late, at risk or due; what ships when; which sprints are off track.
BlockersWhat is blocked, for how long, and what waits on it.
TrendsHow each project's velocity and throughput are moving.
BudgetHow far through its budget or allocation each project is.
StaffingHours needed against reserved over 4, 8 or 12 weeks, and who is free to take on more.
ExceptionsWhich overbooked allocations wait on my decision as a line manager.
Weekly statusWhat happened across my projects this week, in one table and one exportable deck.

Money: what is there today

Not yet in the product

Contract value, bill rates, margin forecasts and a screen to enter a project's budget. Budget is not yet a health dimension.

Why it matters for leadership

Step by step: Portfolio and health and Accounts and programmes in the User guide.